Beachside home - 2 storey

This large two storey home was installed on site within days. The external upper storey walls were pre-fabricated and clad in the Framewayz factory and installed on site within hours. This method significantly reduced build time & scaffold costs.

Wall framing is fabricated precisely in the factory
Wall framing is fabricated precisely in the factory
First floor walls are fabricated and clad in the Framewayz factory
First floor walls are fabricated and clad in the Framewayz factory
Panels are delivered to site on Day 1
Panels are delivered to site on Day 1
Wall panels installed on site
Wall panels installed on site
Wall panels continue to be installed on day 1
Wall panels continue to be installed on day 1
Floor frame is fabricated into cassettes in the factory and craned into position on site
Floor frame is fabricated into cassettes in the factory and craned into position on site
First floor walls delivered to site fully clad & craned into position on day 3
First floor walls delivered to site fully clad & craned into position on day 3
Roof trusses are installed on site on day 4 & 5
Roof trusses are installed on site on day 4 & 5